$251K allocated for Bodenhamer Center lobby renovation

$251K allocated for Bodenhamer Center lobby renovation

By John Mullen
During the May 17 council work session, Gulf Shores City Council heard a recommendation to award the Bodenhamer Center lobby renovations contract to Green-Simmons for $251,000.
Renovations include the following: Demolition and removal of existing reception desk and retail center; Interior wall construction around new cardio equipment area; Removal of existing ceramic tile and vinyl tile flooring in the lobby and replace with new laminated vinyl flooring; New doors and storefront systems; Modified HVAC ducting for new layout.
also, modified/new electrical receptacles, data lines, coax cabling, and saw-cutting the existing slab as required for the new cardio and fitness areas to provide power and data to equipment; New light fixtures; Painting all walls; Installation of new reception desk by the main entrance; Construction of new retail location for city store merchandise; Construction of new coffee bar with cabinetry and casework.