Culvert repairs on Innerarity’s Canal Rd. will start on May 16

Culvert repairs on Innerarity’s Canal Rd. will start on May 16

Culvert repairs will begin north of the intersection of River Road and Perdido Key Dr. on Innerarity Point will begin on May 16, The project consists of replacing an existing culvert crossing, asphalt roadway and multiuse path damaged during Hurricane Sally. The project will be completed within 270 days, weather permitting. River Road will be closed at the project site during construction construction, which will take place 7 a.m. to 5 p.m. Monday through Friday. The project is funded by FEMA with a construction cost of approximately $1.4 million. Quality Enterprises USA is the contractor More info: 850-375-3719.